Pre-Construction Firestop Submittal & Shop Drawing Reviews

What We Actually Check (Most Reviewers Don’t)

  • Correct UL/Intertek system selected for every substrate and penetrating item
  • Annular space and sleeve details match the tested assembly
  • Required forming material, backup material depth, and top-coat on both sides
  • Head-of-wall and perimeter; movement capability calculations
  • Red-line markup with exact deficiency citations

Case Study – 42 Story High-Rise Building

Caught 185 wrong systems in the original submittal package (wrong materials listed, not the correct manufacturer and wrong substrates)
Cost if not caught after installs = estimated $200,000 in time and materials to remove and re-install, 2 month delay (unknown cost of the delay)
Owner now requires our pre-con review on every one of their projects nationwide.